BANK OF NEW ZEALAND

BNZ CENTER I BEAMS

In order that the basement level retail tenancies could be enlarged 2 primary structural beam had to be replaced and removed. The beams were over 1m deep and weighed over 13 tonnes. They had to be inserted beneath an existing occupied retail floor and above two levels of underground carparks. The existing beam had to have concrete encasement blasted from it prior to being cut out and removed from the building. Although not a large project in so far as cost it was definitely one of the more challenging projects. Due to the success of these two beams we are now exploring the options of removing another 8 beams in the same manner.



© 2001 Peck Consultants
Design by Opus Web Design